Three new power plants providing reliable electricity in Cameroon

82,089FansLike
2,966FollowersFollow
2,700SubscribersSubscribe
82,089FansLike
3,122FollowersFollow
2,700SubscribersSubscribe

Updated: March 7, 2021

For many years, Cameroon’s national electricity supply has been notoriously unreliable and subject to power cuts. The last significant electric system outage, which lasted eight hours, occurred last March and affected several of the country’s regions, including the Far North, North, Littoral, Adamaoua, South and Centre regions.

Cameroon power plant

However, three projects financed by the African Development Bank for $121.4 million in 2010-2011 are at last starting to provide long-suffering Cameroonians with much more reliable electricity.

[read_more id="2" more="Read full article" less="Read less"]

Completion of work on transport lines, line maintenance and especially the replacement of wooden electricity transport poles with concrete poles are all part of the system improvements, with the goal to increase the quality and reliability of public access to electricity.

The Lom Panga storage reservoir project is complete, but the dam’s generating plant is still under construction. In the meantime, two other power plants, Kribi and Dibamba, have begun working to strengthen Cameroon’s generating capacity.

In November 2011, the African Development Bank awarded $62.9 million for the construction of Lom-Pangar, the hydroelectric generation’s ‘lungs’ in the country’s East region. The project included the construction of a reservoir (6 billion cubic meters of water retained) for regulating the Sanaga’s flow and optimising generation during low water periods at the Song Loulou plant (335 MW) and the Edea plant (224 MW). The production from these two plants has grown from 450 MW in 2011 to 729 MW now.

A 30 MW hydroelectric generating plant is under construction at the base of the dam. It will be linked to the Bertoua thermal plant by a 105 km 90kV line that should start to work in May 2021 following the installation of an evacuation station and the construction of its four turbines. Lom-Pangar will provide electricity to 150 locations in the region and will significantly reduce power cuts in the area.

“The Lom-Pangar dam will help save water in other reservoirs,” said Theodore Nsangou, the General Director of the Electricity Development Corporation (EDC), in an interview with a government publication in March 2018.

The 216 MW capacity Kribi gas-fired generating plant began to work in 2013 after receiving $32.8 million from the African Development Bank in July 2011 for an expansion project. Its production goal is 330 MW. Currently, the power plant has a 100 km 225 kV transport line connecting it with the Magombe substation in the Edea region in the country’s South region. The plant operates with natural gas (with light fuel oil as emergency backup) from the Sagana South offshore gas field.

During the dry season, the Kribi plant and its nine simple cycle gas turbines are truly the system’s “oxygen”, maintaining the country’s energy flow, particularly to the South’s interconnected system, which receives its electricity from Kribi.

The Kribi gas-fired generating plant and the Dibamba generating plant provide access to electricity for close to half of Cameroon’s population.

The Dibamba heavy fuel oil generating plant was also designed to meet the serious problem of power cuts during the dry season. It was the first of the three plants to receive financial support from the African Development Bank of $25.6 million in April 2010. Built to mitigate the country’s shortage of electricity, high demand quickly outpaced its capacity the day after it began operations.

Located in the outskirts of Douala, Cameroon’s second largest city, Dibamba is an 86 MW thermal generating plant with a 2 km 90 kV transport line linked to the network serving the most remote and densely populated areas in the country’s West region.

With an estimated 23,000 MW hydroelectric production capacity, Cameroon has the second largest hydroelectric potential in Africa and the 18th largest worldwide. The country plans to complete the development of its hydroelectric industries by 2035. Construction of the Nachtigal hydroelectric generating plan began in 2019 and will be complete in about five years, with an estimated generating capacity of 420 MW.

The African Development Bank has awarded a funding package of $154.8 million for the completion of this generating plant. Other development partners, such as the World Bank, the European Investment Bank and Proparco, are also involved.

[/read_more]

WhatsApp Image 2020 12 12 at 17.28.57
Today News Africahttps://todaynewsafrica.com
Today News Africa is a US-based international news organization focused on US-Africa policy and breaking news. Our goal is to provide truthful and exclusive stories to a diverse audience across North America and the African Continent. Subscribe to our news page at https://todaynewsafrica.com/ and Follow us on Twitter @todaynewsafrica

LEAVE A REPLY

Please enter your comment!
Please enter your name here

Trending Now

TRENDING

Confidential U.S. government report concludes Ethiopia Prime Minister Abiy Ahmed leading ethnic cleansing in Tigray region

A confidential U.S. government report has concluded that the government of Prime Minister Abiy Ahmed in Ethiopia along with allied militia fighters are leading a systematic campaign of ethnic cleansing in Tigray."Whole villages were severely damaged or completely erased," the report, first obtained by The New York Times, says.It adds that fighters from the neighboring Amhara region of Ethiopia who moved to Tigray...

Stay connected

[/read_more]

[read_more id="2" more="Read full article" less="Read less"]

error: Alert: Content is protected !!
Share
Tweet
Reddit
Pocket
Share
More